Hello! welcome to the building “ Quality Building Construction Process-2024” tour. It‘s very important to know the different stages of construction, Method, specification and execution process to ensure the quality of your building construction, optimization and best utilization of “Hard Earned money”.
Quality Building Construction Process-2024
followings are some important stages for quality building construction-
Building Construction Process can be divided into 10 important stages-
- Documentation
- Design & Project Planning
- Liaisoning & Structure
- Site mobilization
- Sub-Structure Super
- Structure
- Set Backs & Flooring
- MEP
- Plaster
- Hand Over the final Project
Stage-1. Documentation
Quality Building Construction Process-2024
Whenever a person wants to engaged a company to construct his/ her own dream home. Client and Company must be aware of the proper documentation for future reference. All documents must be signed by both the parties and record it properly.
Followings are some important documents-
- Final and signed BOQ by both the party
- Payment Plan
- Agreement
- Client KYC
- Registry Documents
- Possession documents
- Mutation and Lease documents
- NOC Zoning Plan
These documents will help for –
- Getting approvals drawings from concern authority
- Getting construction Loans if required.
Create-WhatsApp -As WhatsApp is a best way to connect client to different teams of company like design team, execution team, Sales team, account team, customer support team, management team etc. this help to keep updated with Daily progress on design and real time Site Execution with live photographs and videos.
Stage-2. Design & Project Planning
After completing all the documentation, it is important stage to start design of the complete building project and plan the releasing of relevant drawings on different stages. To achieve a perfect building and robust structure it is important to plan the whole project execution in professional way.
The two main teams that play important role are-
-
Design team-
Plan the complete project design as follow-
-
- First it connect to the client to get their requirements and inputs,
- Start Architectural layouting on this basis and finalize it.
- When client completely satisfied with the layout plan and approve.
- Structural design & Liaisoning process starts.
- As soon As Sanctioned Drawing Received, GFC drawings get started and released to the Site for Execution.
- Parallelly 3D team Start 3D visualization for façade.
- After finalization of above drawings MEP drawings start and finalized with the consent of client and released to the site.
- Similarly all the interior designs and drawings start and finalized stage wise and released at different stages.
2. PMC Team –Which plan the complete project execution on site. Divided complete Project into detailed phases and stages as-
-
- Project planning
- BOM– Material Procurement planning
- Material Handling plan
- Waste management
- Risk Assessment plan
- Team planning
- PMC Head
- Quality Eng.
- Project Eng.
- Site Eng.
- Fore Man
- Skilled & unskilled manpower planning
Stage-3. Liaisoning & Structure-
Different Areas are controlled under different development authorities. We need to get sanctioned drawings for our building Construction. As soon as all the layouts freeze and finalized with the mutual consent of design team and Client approval, it goes to submit in Concern Authority in prescribed format, it’s scrutinized by authority and if all the drawings and information found correct, An approval on drawings released by the Concern Authority. At the same time all detailed structural designs and drawings are prepared checked and released.
Stage-4. Site mobilization-
Under this stage all the necessary steps covered to start a project and complete smoothly timely and accurately. followings are some key points covered under this stage-
-
- Site inspection
- Site Cleaning
- Water and Electricity provision
- Site barricading
- Labour hutment and store making
- Caution board
- Health & safety guidelines board
- PPE kit
- First Aid Box
Stage-5. Sub-Structure
Quality Building Construction Process-2024
For Stilt/ Gr. Floor and Above
- Site Demarcation
- Earthwork/ Excavation
- Footing & Column layout
- Dressing & compaction & ATT
- PCC
- Layout Verification
- Bar binding Shuttering of footing
- Casting
- Curing P
- Pedestal layout work
- Pedestal bar binding
- Shuttering Casting
- UGT
- Lift Pit
- Foundation Brick work if required
- Backfilling
- ATT & Compaction
- PCC below plinth beam
- Plinth beam layout
- Bar binding
- Shuttering
- Casting.
- Curing
For Basement and above floors-
- Site Demarcation
- Earthwork/ Excavation
- Footing & Column layout
- Dressing & compaction & ATT
- Layout work
- UGT, Sump & Lift Pit
- PCC
- Pre Construction Water Proofing
- Layout Verification
- Bar binding
- Shuttering
- Footing & Raft Casting
- Curing
- Layout of Retaining wall & Column
- Bar Binding
- Shuttering
- Casting
- Curing
- Backfilling,
- ATT & Compaction-
- RWH
Stage-6. Super Structure-
Quality Building Construction Process-2024
- Column Layout
- Column Steel work
- Form work
- Checking & approval (At all stages)
- Casting
- DE shuttering
- Curing
- Outer Wall Brick work
- Shuttering for Slab (Taping, Oiling and joints finishing)
- Steel work Slab
- Conduit and Sleeve
- Checking & Approval
- Casting
- bund wall
- Curing
- DE shuttering
- Internal Brick work
- Lintel Above Opening Door/ Window
- Frame fixing
- MEP- Conduit
- Water Proofing in Sunken Areas
- Internal Plaster work
Stage-7. Set Backs & Flooring
- Footings & Columns
- Brick Work
- Plaster
- Curing
- Flooring-
- ATT, Compaction & leveling,
- PCC
Stage-8. MEP-
- ELECTRICAL
- Conduiting
- Wiring
- Fixture & Fittings
- Testing & Commissioning
- PLUMBING
- under Ground Pipe lines
- Water Supply Connections
- UGT Connections
- OHT Connections
- Fitting & Fixtures
- Testing & Commissioning
- AIR-CONDITIONING
- LIFT
Stage-9. Plaster
- Scaafolding
- Outer plaster
- Water Proofing Coating
- Internal Plaster
Stage-10. Hand Over
Quality Building Construction Process-2024
- Project Execution Team Visit
- Inspection & Checking
- Snag list
- Rectification
- Client invitation
- Inspection & Checking
- Snag list
- Rectification
- Hand Over Process
- Final Documents
- NOCs
- Thanks & Wishes
Quality Building Construction Process-2024
Hey, I enjoyed reading your posts! You have great ideas. Are you looking to get resources about Website Design or some new insights? If so, check out my website Webemail24